MEPCO New Connection — Apply Online, Documents & Demand Notice Guide | Online MEPCO Bill
New Connection

MEPCO New Connection — Complete Application Guide

Everything you need to apply for a new MEPCO electricity connection — required documents, the Demand Notice process, expected timelines, and how to track your application from start to finish.

ENC PortalApply fully online, upload documents
MEPCO Smart AppApply & track from your phone
CFC Office VisitIn-person at your local center
Connection Categories

MEPCO classifies connections by load

Your approval authority and processing time depend on which category your required load falls into.

Category 2

Above 15 kW – 400V limit

Larger homes, commercial units, and small industrial connections.

  • Higher-level approval required
  • Additional technical review

Category 3

Above 400V

Large industrial and bulk connections. Applicant must arrange their own transformer.

  • Requires owned transformer
  • Longest approval chain
Process

From application to activation

The typical journey for a Category 1 (domestic/small commercial) connection.

01

Gather your documents

Collect your CNIC, property or tenancy proof, a neighbour's recent bill copy, and a wiring test report from a licensed contractor.

02

Submit your application

Apply via the ENC Portal, MEPCO Smart App, or in person at your nearest Customer Facilitation Center. You'll receive a Tracking ID.

Same day
03

Document verification & site survey

MEPCO staff verify your documents and conduct a feasibility inspection at your premises.

Varies by workload
04

Demand Notice issued

Once approved, your file moves for final sign-off and a Demand Notice is generated with your connection charges and security deposit.

05

Pay at a designated bank

Pay the Demand Notice amount and submit the paid receipt to your MEPCO office (or upload it via the portal/app).

~2 days
06

Meter installation & activation

After payment verification, MEPCO issues installation orders, arranges the meter, and connects your supply.

~1–2 weeks
Documents

What you'll need to apply

Requirements differ slightly depending on whether you own or rent the property.

1Attested CNIC copy of applicant
2Attested CNIC copy of a witness
3Property ownership document copy
4Neighbour's recent electricity bill copy
5Wiring test report (licensed contractor)
6Recent passport-size photograph
1Attested CNIC copy of applicant
2Attested CNIC copy of a witness
3Neighbour's recent electricity bill copy
4Wiring test report (licensed contractor)
5Owner's No Objection Certificate (NOC)
6Owner's CNIC copy (front & back)
Track Your Application

Check your Demand Notice & application status

Enter your Tracking ID or CNIC to jump straight to your application status on the official ENC portal.

Free Official ENC Portal

FAQs

New connection questions, answered

For small residential or commercial loads (Category 1, up to 15kW), the process typically takes a few weeks from application to installation, depending on document verification, demand notice payment, and equipment availability. Larger loads requiring higher approval levels can take longer.

Tenants must additionally upload a No Objection Certificate (NOC) from the property owner along with the owner's CNIC (front and back). The rest of the application process is the same as for owners.

A Demand Notice is a payment voucher issued after your application is verified and approved. It lists your connection charges and security deposit, and must be paid at a designated bank before installation proceeds.

Yes. You can apply entirely online through the ENC Portal or MEPCO Smart App by uploading scanned documents. Some offices may still ask you to submit a printed copy of your application for their records.

Use the Tracking ID (Application Reference Number) issued when you submitted your application, along with your CNIC, to check your status on the ENC Portal at any time.

Connection charges vary by category and area. Your exact Demand Notice amount depends on load requirement, urban/rural location, and infrastructure needs — this is calculated by MEPCO at the survey stage, not a fixed published number.